St. Thomas motorists heading downtown on Veterans Drive discovered both east and westbound lanes open to traffic on Saturday after a paving project was completed. The work is part of Phase 2 of the Veterans Drive Improvement project.

Phase 1 was finished by the American Bridge Company in August 2020, well before its completion date of July 2021, at a cost of $45 million.

The scope of work included roadway widening, pavement reconstruction, seawall construction, drainage improvements, lighting, installation of a new expanded promenade and landscaping.

The design for Phase 2 is scheduled to be completed in 2021, with an estimated cost of $100 million.

READ MORE: VI SOURCE

U.S. VIRGIN ISLANDS WEATHER

VITFF Releases Update on Virgin Islands Track and Field Athletes

VI News Staff
1 year ago

Appeals court agrees to speed up Justice Department's appeal of order...

VI News Staff
2 years ago

$750,000 Grant Funds State-of-the-Art Lineman Training for V.I. Water...

VI News Staff
9 months ago

HUD Awards $195,000 for 17 New Housing Vouchers in U.S. Virgin Islands

VI News Staff
2 years ago

US seizes stolen funds from suspected North Korean hackers

VI News Staff
2 years ago