First phase of ESHS redevelopment completed ahead of schedule

Demolition and site clearance of old foundations at the Elmore Stoutt High School has been completed ahead of the January 7 deadline.

The project was undertaken by Sandwise Limited as they won the $136,079.50 contract to provide the demolition and clearance services.

The works began on December 10 and since then, workers have been working from 8 o’clock in the morning to four in the afternoon to complete the task during the allotted time frame.

While demolition was happening, BVI News noticed workers drilling through the old concrete foundation in the mornings and using an excavator to remove the heavy stones once the drilling stopped in the afternoon.

The debris was loaded into dump trucks and removed from the site.

Over the last few days, the workers levelled the area and poured asphalt on various sections.

READ MORE: BVI NEWS

U.S. VIRGIN ISLANDS WEATHER

Bryan Nominates Julio Rhymer as OMB Director, Discusses Vendor Payment...

VI News Staff
1 year ago

Behavioral Health Bill Moves Forward, But Provision Allowing Authoriti...

VI News Staff
3 years ago

Governor Bryan Addresses School Safety, Historic Land Acquisition, and...

VI News Staff
9 months ago

Territory’s Mental Health Response Under Scrutiny at St. Croix Crime T...

VI News Staff
1 year ago

CDB predicts GDP growth in borrowing nations like BVI

VI News Staff
4 years ago