‘Students & teachers of ESHS coming back home in 2022’- Premier - as demolition & site clearing work completed ahead of schedule

ROAD TOWN, Tortola, VI- “Our students and teachers of ESHS are coming back home in 2022,” exclaimed Premier and Minister of Finance Honourable Andrew A. Fahie (R1), as he celebrated the completion of the demolition and site clearing work at Elmore Stoutt High School (ESHS) compound.

Sand Wise Limited was awarded $136,079.50 for the demolition and debris removal at ESHS. The contract was signed on December 2, 2021.

Project completed ahead of time!

And, according to Premier Fahie in a Facebook post on January 7, 2022, the project was completed ahead of time.

“You cannot get any clearer than this! The 1st phase of the Redevelopment of the Elmore Stoutt High School Campus since the destruction of many buildings by Irma in 2017 has been completed ahead of schedule.

“All the old foundations were demolished and removed.”

Premier Fahie continued that the contractor, Sand Wise Ltd, did an outstanding job and that the Minister for Education, Dr The Honourable Natalio D. Wheatley (R7) has surveyed the now cleared property and is pleased.

“Now on to phase two as it is soon time for the construction of the new buildings. To GOD alone be all the GLORY!!! We're in this together,” Premier Fahie said.

READ MORE: VIRGIN ISLANDS NEWS ONLINE

U.S. VIRGIN ISLANDS WEATHER

Public Hearing Thursday for Proposed Condo Community in Caret Bay

VI News Staff
2 years ago

St. Croix man accused of sexually assaulting minor

VI News Staff
1 year ago

School Bus Service to Resume Sept. 13 on St. Croix and Sept. 7 in St....

VI News Staff
4 years ago

GERS board votes to delay 3% increase in employer contributions by nin...

VI News Staff
1 year ago

Florida Attorney General sues Snapchat over child safety violations

VI News Staff
11 months ago